By providing your contact information to Team Citron, your personal information will be processed in accordance with Team Citron's Privacy Policy. By checking the box(es) below, you consent to receive communications regarding your real estate inquiries and related marketing and promotional updates in the manner selected by you. For SMS text messages, message frequency varies. Message and data rates may apply. You may opt out of receiving further communications from Team Citron at any time. To opt out of receiving SMS text messages, reply STOP to unsubscribe.
Thank you for your message. We will be in touch with you shortly.
Explore Our Properties
Seafoam stucco house entrance with clay roof tiles, a timber door, pale limestone steps, and sculptural tropical planting.

In Shores Estates, the Sewer Bill Arrived Before the Sewer

October 22, 2026

"And then, once we close it out, then by next year we start talking about the connection." Delroy Peters, the Miami Shores Public Works Director, said that to the Biscayne Times this summer. He expected the Shores Estates sewer project to be finished by December 2026.

The neighborhood sits roughly between the Miami Shores Country Club, NE 107th and 108th streets, Biscayne Boulevard and the Biscayne Canal. The pipes are in the ground. The pump station on the former Miami Shores Motel site at 10500 Biscayne Boulevard passed its testing in September. But no home can connect yet, and the assessment that pays for the system is already running.

The Part That Started First: The Assessment

The project cost about $3 million and broke ground in June 2025. It is the first residential septic-to-sewer conversion in the Village's history. At a special meeting on September 15, 2025, the Village Council held a public hearing on a non-ad valorem wastewater assessment for Shores Estates. Citizen Portal's coverage of that meeting reported that the Council approved the assessment along with a 20-year financing plan. Staff said grants cover much of the construction, and residents carry roughly 25% of the total cost.

In August 2026, the Biscayne Times reported that homeowners were already being charged $1,163 a year per home for the new sewer lines, even though the system hadn't been switched on.

The Part That Hasn't Started: Home Connections

The Village's September update said plainly that the system is not yet open for residential connections. It also told residents not to start a connection or septic abandonment until the Village gives formal notice.

North Miami will run the system once it's live, and the Village says North Miami's Sewer Department will set the connection timelines.

The Part Nobody Has Seen Yet: What Connecting Costs

Cost is the least settled piece of the conversion. The table shows where each part stood heading into the end of October 2026.

Piece of the connection Status in late October 2026 Where it comes from
North Miami utility connection charge Homeowners won't be charged one, according to North Miami Assistant City Manager Katia M. Philippeaux Biscayne Times, August 2026
Leftover project money Village Manager Esmond Scott said $1 million left over from the project would offset those costs Biscayne Times, August 2026
Assistance for connection and septic abandonment State-sourced funds; how they're distributed is still being worked out with FDEP and needs Council approval Village project page, September update
How the program works Under consideration: a Village-managed program, or homeowners hiring their own licensed professionals Village project page, September update
Program details Still a draft as of October; Village said it planned to share details by the end of the month Village project page, October update

The first row is easy to read too broadly. "No connection charge" refers to the utility's fee. It doesn't cover the plumbing on the homeowner's side of the property line or closing out the old tank. The Village's own updates describe the available money as offsetting "a portion" of connection costs. As a reference point, Miami-Dade County's District 1 septic-to-sewer program page puts a typical homeowner's private-side connection at about $10,000 to $15,000. That estimate includes plumbing, septic abandonment, permits and fees. It's a countywide estimate, not a Shores Estates quote. It does show the size of the cost that the unfinished assistance program is meant to cover in part.

The work itself involves several agencies. The Village advises using a licensed contractor for septic abandonment. The Florida Department of Environmental Protection oversees it statewide, and the Miami-Dade office of the Department of Health handles permits and inspections. Building and plumbing permits for Shores Estates will go through Miami Shores, which is why the Village plans to publish its own process instead of pointing residents to North Miami's.

The Street Out Front Is Also Mid-Change

Buyers touring in late October will see unfinished work, and the reason is a scheduling change. The October update put milling and paving from NE 11th Court through NE 10th Court on the calendar for October 19 through 23. On NE 105th Street, the plan has narrowed. Crews will fix the sewer trench, potholes and other damage from the project, but the broader road and swale restoration is being left for a stormwater improvement project the Village describes as imminent. The temporary opening in the wall at the east end of NE 105th Street won't be rebuilt until that drainage work is done. The Village plans to propose a temporary barrier for now.

That adds a second project to the house's future. The Village hasn't given a start date, so it's one more thing a buyer should ask about directly.

Questions to Settle Before the Contract Is Signed

Because each piece of the conversion is on a different schedule, the useful questions are about dates and documents:

  1. Assessment. What is the current annual amount on this parcel, how many years remain under the 20-year plan, and how will the contract handle it at closing?
  2. Notice. Has the Village or North Miami sent written notice of availability?
  3. Program. Has the Council approved the connection program? Has the seller signed up for the Village-managed option or told the Village they'll handle the work themselves? The September update asked residents to share that preference.
  4. Tank. When was the septic system last serviced? The house will rely on it until the connection is made.
  5. Street. Is this lot on NE 105th Street or near the east-end wall, where restoration has been put off until the drainage project?

Why This Matters Beyond 99 Homes

More than 90% of properties in Miami Shores still run on septic, according to the Village's 2022 strategic plan as reported by the Biscayne Times. Esmond Scott told the paper the next project would cover 240 homes in southeastern Miami Shores. At a meeting in June 2026, Citizen Portal reported that the Council discussed candidate boundaries including 12th Avenue to the bay and a corridor from 91st Terrace to 96th Street. Members asked for engineering and cost comparisons before choosing one. The Village's FY2026 proposed budget sets aside $5 million of $7 million in Clean Water Grants to start funding the second identified area.

FAQ

Can a Shores Estates homeowner connect to the sewer now? No. As of the Village's fall updates, the system wasn't open for residential connections, and residents were told to wait for formal notice before starting any connection or septic abandonment work.

Who runs the system once it opens? North Miami. Homes will connect to its wastewater infrastructure.

Where does the Village post project updates? On its Shores Estates Septic to Sewer Conversion page, which carries dated construction updates from Public Works. The department can be reached at 305.795.2210.

This post is general information, not legal, tax or financial advice. Assessments, deadlines and assistance terms can apply differently to each parcel, so please confirm your own situation with the Village, your attorney or your closing professional.